The facade of the building is coming together, the extrerior is almost completly enclosed(windproof). The last exterior glass will be installed in the coming days, apart from some wood panels which still need to be replaced by special windowframes. The tourniquet is placed and the first two elevators are constructed, this makes the building coming together bit by bit. making the end at an arm reach.
The building scaffolding is removed at the south side of the building and at the north side is a speedgate installed.
At the public staircases the glass balustrades are mounted and the first bambooslats are placed against the walls, allowing you to imagine how the finished product will look.
In the coming weeks the focus will be more on installing the bamboo and the first cealings will be finished.