Last week the ramp of the parking garage was poured and underfloor heating was placed. In the winter the underfloor will be heated to prevent the ramp of becoming icy.
The last part of the of the cellar deck was poured. Soil will be placed upon the cellar deck so it isn’t visible. A part of the parking garage will be located underneath the street.
Furthermore, A few parts of the ground floor were poured and pillars were placed in the front of the hotel wich is taking shape now.